DGD Valero

Durr Heavy Construction was hired to by Group Industries to help complete Diamond Green Diesel’s Site Improvement Project in Norco, LA. Durr graded out areas along their Warehouse and Administration Buildings for new asphalt to be placed, and graded out areas along the main roadway into the facility. Durr also placed new curb and gutter for landscaping areas, excavated out existing material, and placed a new limestone base for a 13,000CY new parking lot to be asphalt paved. Along with this site prep work, Durr installed over 3,400 LF of new drainage pipe to ensure proper drainage for the site improvements made. Work was completed in January 2022.